Construction Update: October 4, 2018

السلام عليكم و رحمة الله و بركاته

With the help of Allah SWT and with all of your prayers and support we are now MashaAllah very close to open the new prayer hall. I should be able to confirm the date by late next week after getting confirmation from the Fire Marshall In Sha Allah. 

Last week we completed the following tasks:

  1. Mihrab: Started speaker and electrical work 
  2. Finishing up any additional electrical, low current wiring, testing CCTV, speakers adjustments on the ceiling fans, adjustments on air vents, etc..
  3. Finishing up paint work
  4. Pour concrete for the main gate
  5. Pour concerate for the Fire thank foundation

This week we will try to start and complete the following tasks:

  1. Complete Paint touch ups
  2. Start the civil work for Fire tank
  3. Start to install stalls in the washrooms

Major Milestone(s):

  1. Installation of Fire tank
  2. Occupancy Certificate